update: February, 2025
Across the 10 Blocks currently under construction at Poet & Perth, siding is being completed on the final building, as well as the drywall. We are getting close to the finish line!




update: November, 2024
Lots of developments from Poet & Perth over the last year:
Block 1 – Interior rough in stage, with plumbing completed and HVAC started. Exterior brick completed with siding to begin shortly.
Block 2 – Interior taping finishing, with exterior brick completed and siding almost completed.
Block 3 – Interior drywall underway, with exterior brick completed and siding just beginning.
Block 4 – Interior rough ins completed and insulation to begin soon. Exterior brick has been completed and siding will begin soon.
Block 5 – Interior cabinets being installed this week. Exterior brick and siding completed, with exterior railings to be installed shortly.
Block 14 – At the framing stage, with trusses to be set by end of week.
Block 15 – At the framing stage, with prefabbed walls to be set in place soon.
Block 18 – Interior rough in stage underway. HVAC and plumbing completed with electrical now underway. Exterior brick underway and to be completed soon.
Block 19 – Finishing stage with interior carpet and final paint to be completed. Exterior brick and siding also completed. Rear decks to be installed next week.
Block 20 – Interior rough in stage, with plumbing started with HVAC and electrical to follow.



update: July, 2023
Welcome to Poet & Perth! Earthworks are currently in progress across the site as we prepare for phase 1 construction.