Lackner Ridge
Construction Updates

 

 

Need Assistance? Don’t hesitate to reach out, we are here to help!

Elaine Blackburn Ribeiro
Customer Experience Concierge
519-658-6656 Ext. 332
concierge@heritagehomes.com 

 

update: June, 2025

Wynstone (Building 1100) and Hillcrest (Building 1200)

  • Exterior Façade is 95% complete with balcony railings and main entrance canopy outstanding
  • Hardscape and landscape will be commencing by end of June and wrapping up in July/beginning of August
  • Suite finishes on all levels are 90% complete and are progressing well with hardware, final paint, and appliance install
  • Common area finishes and corridor are progressing well and are 70% complete on all levels
Procore
0CB3EAF2 E8A2 4159 BFE5 40D7D7D80B7C

update: April, 2025

Construction of both Wynstone (Building 1100) and Hillcrest (1200) is well underway, inside and out! We have begun installing Kitchen cabinets as well as Bathroom cabinetry and fixtures.

Interior Finishes 1100 and 1200
Bathroom Cabinets and Fixtures 1100 and 1200
Front Entrance 1100 and 1200

update: September, 2024

Progress at Wynstone (Building 1100) and Hillcrest (Building 1200) continues. The concrete foundation is almost complete. Load boarding masony walls on level 1 have begun on the east end, with the west end to follow later this month. Precast floors are next in the progress and expected to begin over the course of the summer.

Procore

update: November, 2023

We have been landscaping the exterior of Lackner Ridge Cityview (Building 1201) and Sonterra (Building 1101). The third building at 1000 Lackner Blvd. is underway, and we are gearing up to start construction on the fourth and fifth buildings.

DCIM101MEDIADJI_0943.JPG
DCIM101MEDIADJI_0949.JPG

update: July, 2023

Congratulations to our homeowners at Cityview (Building 1201) and Sonterra (Building 1101), as we have handed out all keys and are in the midst of final closings for both buildings.

We are making great progress at Westvale (Building 1000), the concrete walls in the underground parking garage are now complete and the first floor masonry walls are underway.

dji_fly_20230714_094742_746_1689342467779_photo_optimized
dji_fly_20230714_094526_736_1689342334943_photo_optimized
dji_fly_20230714_094946_751_1689342592893_photo_optimized

update: April, 2023

We’ve welcomed the first occupants of Cityview (Building 1201) and are preparing to hand out keys for Sonterra (Building 1101) in the coming months.

Westvale (Building 1000) is progressing well, and we now have over half the footings poured and a quarter of the foundation walls have been placed.

dji_fly_20230414_150848_512_1681499336274_photo_optimized

update: January, 2023

Construction continues to progress at Lackner Ridge. Cityview (Building 1201) continues to be the furthest along in progress with a lot of work and finishing occurring on the interior.

Sonterra (Building 1101) now has more stonework progressing and we have now begun work on Westvale, building 1000 with site grading underway.

dji_fly_20230110_112508_219_1673367917912_photo_optimized
dji_fly_20230110_112602_223_1673367969242_photo_optimized
dji_fly_20230110_112424_213_1673367878928_photo_optimized

update: November, 2022

Work continues to progress at Lackner Ridge! Cityview (Building 1201) is furthest along in progress with exterior finishes almost done and installment of the balcony railings in progress. Sonterra (Building 1101) continues to progress as well with brick and stone work underway.

slider image 45574 orig cropped
slider image 45573 orig cropped
slider image 45572 orig cropped
slider image 45571 orig cropped

update: July 2022

We have started interior framing on Sonterra (Building 1101) and work is continuing on the exterior of Cityview (Building 1201).

DCIM100MEDIADJI_0564.JPG
DCIM100MEDIADJI_0552.JPG

update: May, 2022

Construction is progressing at Lackner Ridge and we’re happy to share that the roof is now on for Cityview (Building 1201). Construction is also progressing well at Sonterra (Building 1101).

dji_export_1651839063457
dji_export_1651839031989

update: March, 2022

We are excited to share that construction of the Cityview (Building 1201) has reached the fourth and final floor! Construction is also progressing nicely at  Sonterra (Building 1101), where construction on the 3rd floor will be starting shortly.

Drone_Mar_3.22
Drone_2_Mar_3.22

update: January, 2022

Lots of progress has been made at Lackner Ridge!

Cityview (Building 1201) is on the 3rd floor and Sonterra (Building 1101) is not far behind as it is on the 1st floor.

WEB1
WEB3
WEB2
WEB4

update: November, 2021

Construction is progressing at Lackner Ridge! Here are some recent photos of the progress.

20211110_101904
20211110_102226
20211110_102417

update: October, 2021

Some great aerial shots of the progress at Lackner Ridge.

DCIM100MEDIADJI_0173.JPG
DCIM100MEDIADJI_0168.JPG
DCIM100MEDIADJI_0164.JPG
DCIM100MEDIADJI_0176.JPG

update: August, 2021

Construction is moving forward at Lackner Ridge. The foundation is almost complete at Cityview (Building 1201) and our construction team is also getting ready to start the foundation at Sonterra (Building 1101).

LR_Aug 11_1_
LR_Aug 11_2_
LR_Aug 11_3

update: July, 2021

We are pleased to announce that we have started construction on Cityview (Building 1201)!

This is just the beginning of what is to come in this amazing community.

We are also now sold out of all units at Cityview and Sonterra and on our way to being sold out at Westvale!

MicrosoftTeams image1

update: February 2021

Welcome to 2021! We know that this is going to be a  busy year at Lackner Ridge and we are happy that you have chosen to be a part of the Lackner Ridge Family! We’re very excited to start construction at Lackner Ridge and at this time are expecting to start construction on Cityview and Sonterra in 2021. Keep an eye out for updated pictures throughout the construction process.

Capture3

Reid’s Heritage Homes Corporate Office

700 Jamieson Parkway Unit 103,
Cambridge, ON 
N3C 4N6

Phone

(519) 658-6656

Fax

(519) 654-9746

Reids Logo

HCRA LICENSE NUMBER 13651

©  REIDS HERITAGE HOMES

PRIVACY POLICY SITE BY 52 PICK-UP INC

Thank you for registering.