update: June, 2026
Argyle Village construction update: From completed exteriors and fresh landscaping underway, to new occupancies and homes entering the finishing stages. Each block at Argyle Village is moving forward and bringing this vibrant new community closer to completion. None of this would be possible without the dedication, craftsmanship, and hard work of our site teams and trade partners, who continue to bring our communities to life.
Check out the latest updates below:
Block F – Landscaping is underway and exterior construction is complete.
Block E – Occupancies have begun.
Block D – Pre-Delivery Inspections begin next week, with occupancies starting in late June. Exterior construction is nearing completion.
Block C – Insulation and drywall are nearing completion, while countertops and flooring are now underway. Exterior siding continues to progress.
Block B – Rough-in mechanical trades have begun, with siding set to start by late June.
Block A – Masonry is nearly complete, paving the way for mechanical rough-ins.
update: April, 2026
Argyle Village construction update: The team has been busy across all blocks.
- Block A: Framing is finishing up.
- Block B: Shingling is complete and ready to begin rough-ins.
- Block C: Basement concrete is poured and ready to start rough-ins.
- Block D: Currently in rough-in stages.
- Block E: Drywall is almost complete; finishes have started.
- Block F: Two model homes are in the finishing stages; siding is being worked on and the Design team is in the staging process.
- Upcoming milestone: Two model homes will open in Summer 2026.
- Landscaping timeline: Landscaping for Block F will be underway in May, welcoming visitors this summer.
update: December, 2025
- Block E & F: Mechanical, insulation and drywall trades are underway.
- Block D: Framing is working on the top floor. Expect to have the roof completed by the holiday break!
- Block C: Foundation, underground services, precast landings and stairs complete! Framing has begun with the foundation being capped for the holiday break!
- Block B: Foundation and underground services complete. Precast landings and stairs are now installed!
- Block A: Foundation poured and underground services are underway.
update: September, 2025
Here are the latest developments from Argyle Village:
- Block D, E and F: all footings completed
- Block F: all foundation walls are completed, underground plumbing and conduit are completed and outside water collection system is currently being worked on
- All porches are being poured with concrete the week of September 22
- Block E: half the lower walls were poured the week of September 15
update: May, 2025
Curbs are in and paving is complete!
update: January, 2025
Site servicing has begun! Installation of underground services (water, sanitary, storm) to be completed between now and April!