Argyle Village
Construction Updates

 

Need Assistance? Don’t hesitate to reach out, we are here to help!

Elaine Blackburn Ribeiro
Customer Experience Concierge
519-658-6656 Ext. 332
concierge@heritagehomes.com 

update: December, 2025

We are full steam ahead in all blocks at Argyle Village:
  • Block E & F: Mechanical, insulation and drywall trades are underway.
  • Block D: Framing is working on the top floor. Expect to have the roof completed by the holiday break!
  • Block C: Foundation, underground services, precast landings and stairs complete! Framing has begun with the foundation being capped for the holiday break!
  • Block B: Foundation and underground services complete. Precast landings and stairs are now installed!
  • Block A: Foundation poured and underground services are underway.
DCIM100MEDIADJI_0185.JPG
DCIM100MEDIADJI_0182.JPG
DCIM100MEDIADJI_0183.JPG
DCIM100MEDIADJI_0184.JPG

update: September, 2025

Here are the latest developments from Argyle Village:

  • Block D, E and F: all footings completed
  • Block F: all foundation walls are completed, underground plumbing and conduit are completed and outside water collection system is currently being worked on
  • All porches are being poured with concrete the week of September 22
  • Block E: half the lower walls were poured the week of September 15
DCIM100MEDIADJI_0110.JPG
DJI 0111 scaled

update: May, 2025

Curbs are in and paving is complete!

default
default

update: January, 2025

Site servicing has begun! Installation of underground services (water, sanitary, storm) to be completed between now and April!

IMG_2772
default

Reid’s Heritage Homes Corporate Office

700 Jamieson Parkway Unit 103,
Cambridge, ON 
N3C 4N6

Phone

(519) 658-6656

Fax

(519) 654-9746

Reids Logo

HCRA LICENSE NUMBER 13651

©  REIDS HERITAGE HOMES

PRIVACY POLICY SITE BY 52 PICK-UP INC

Thank you for registering.