Argyle Village
Construction Updates

Need Assistance? Don’t hesitate to reach out, we are here to help!
Elaine Blackburn Ribeiro
Customer Experience Concierge
519-658-6656 Ext. 332
concierge@heritagehomes.com
update: December, 2025
We are full steam ahead in all blocks at Argyle Village:
- Block E & F: Mechanical, insulation and drywall trades are underway.
- Block D: Framing is working on the top floor. Expect to have the roof completed by the holiday break!
- Block C: Foundation, underground services, precast landings and stairs complete! Framing has begun with the foundation being capped for the holiday break!
- Block B: Foundation and underground services complete. Precast landings and stairs are now installed!
- Block A: Foundation poured and underground services are underway.
update: September, 2025
Here are the latest developments from Argyle Village:
- Block D, E and F: all footings completed
- Block F: all foundation walls are completed, underground plumbing and conduit are completed and outside water collection system is currently being worked on
- All porches are being poured with concrete the week of September 22
- Block E: half the lower walls were poured the week of September 15
update: May, 2025
Curbs are in and paving is complete!
update: January, 2025
Site servicing has begun! Installation of underground services (water, sanitary, storm) to be completed between now and April!