Argyle Village
Construction Updates
Need Assistance? Don’t hesitate to reach out, we are here to help!
Elaine Blackburn Ribeiro
Customer Experience Concierge
519-658-6656 Ext. 332
concierge@heritagehomes.com
update: September, 2025
Here are the latest developments from Argyle Village:
- Block D, E and F: all footings completed
- Block F: all foundation walls are completed, underground plumbing and conduit are completed and outside water collection system is currently being worked on
- All porches are being poured with concrete the week of September 22
- Block E: half the lower walls were poured the week of September 15


update: May, 2025
Curbs are in and paving is complete!


update: January, 2025
Site servicing has begun! Installation of underground services (water, sanitary, storm) to be completed between now and April!

